Bruce EVS3231 Installation Guide Page 3

  • Download
  • Add to my manuals
  • Print
  • Page
    / 10
  • Table of contents
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 2
(
Mechanically Fastened/Staple-Down Installations)
Do not install over floors that exceed one layer, as the thickness of the flooring materials will prevent an adequate mechanical bond.
Make certain that the subflooring materials meet minimum requirements.
• Some tile products may be too brittle for staple penetration. Always test an area for breakage before proceeding.
IV. INSTALLING THE FLOOR
G
eneral Installation Tips
N
OTE: When installing UNFINISHED engineered flooring, allow a minimum of 72 hours adhesive curing time before applying seals,
stains and finishes to unfinished flooring. Test the moisture content of the wood in accordance with the stain/finish manufacturer’s
recommendations.
Do not staple or mechanically fasten products that exceed 5(13 cm) in width.
Floor should be installed from several cartons at the same time to ensure good color and shade mixture.
When possible, preselect and set aside boards that blend best with all horizontally mounted moldings used to assure a uniform
nal appearance. Install these boards adjoining the moldings.
Be attentive to staggering the ends of the boards at least 4–6(10–15 cm), when
possible, in adjacent rows (Figure 4). This will help ensure a more favorable overall
appearance of the floor.
When installing engineered products of uniform length, begin the rows with starter
boards cut to various lengths. Avoid staggering the rows uniformly to prevent
stair-stepping. Boards cut from the opposite end of the row may be used for the
n
ext starter boards.
Always allow a minimum 1/4(6 mm) expansion around all vertical obstructions.
Allow 1/2(13 mm) for floating floors.
N
OTE: (For Glue Down Installation) When installing products wider than 3-1/4(8 cm),
apply a bead of recommended wood glue to all of the end grooves prior to installing into
the adhesive. (For Staple Down Installation) When installing products wider than
3
-1/4 (8 cm) but not to exceed 5(13 cm), apply a bead of recommended wood glue
to all of the end grooves prior to stapling down.
STEP 1: Doorway and Wall Preparation
(All Installation Methods)
U
ndercut door casings and jambs. Remove any existing base, shoe mold or doorway
thresholds. These items can be replaced after installation. All door casings and jambs
should be undercut to avoid difficult scribe cuts (Figure 5).
S
TEP 2: Establish a Starting Point
(All Installation Methods)
Installation parallel to the longest wall is recommended for best visual effects;
however, the floor should be installed perpendicular to the flooring joists unless the
subfloor has been reinforced to reduce subfloor sagging.
When possible, always begin the layout or installation from the straightest wall,
generally an outside wall.
In at least two places, at least 18(46 cm) from the corner, measure out equal distance from the starting wall (Figure 6) and snap
a chalk line. The measurement must be the sum of the width of the flooring plus an additional 3/8(9.5 mm) to allow for 1/4
(6 mm) expansion space and the width of the tongue. Allow 1/2(13 mm) expansion when installing floating floors. Continue to
S
tep 3; Staple, Glue or Floating.
STEP 3: Installing First & Second Rows
(Mechanically Fastened/Staple-Down Installations)
Use the longest, straightest boards available for the first two rows. For random and
alternate width products, use the widest plank for the first row. Align tongue of first
row on chalk line. The groove should be facing the starting wall. Pre-drill 1/2
(13 mm) from back (groove) edge, 1–2(2.5–5 cm) from each end, and at 6
(15 cm) intervals when possible (Figure 7). Fasten using 4 or 6d finishing nails or
1(2.5 cm) pneumatic finish nails/brads. Countersink the nails.
Pre-drill and blind-nail at a 45° angle through the tongue of the first row every
1–2 (2.5–5 cm) from the ends and spaced in 3–4 (7.6–10 cm) intervals.
Countersink nails to ensure flush engagement of groove with the following row(s).
Continue blind nailing using this method with following rows until stapler can be
used. Alternatively use a pneumatic finish nailer and install nails/brads at the same
intervals with a minimum length of 1(2.5 cm).
End-joints of adjacent rows should be staggered a minimum of 4–6(10–15 cm),
when possible, to ensure a more favorable overall appearance (Figure 4).
STEP 4: Installing the Floor
(Mechanically Fastened/Staple-Down Installations)
Always use the recommended stapler for the specific product being installed (see
“Installation Applications”). Use a minimum 1(2.5 cm) staple recommended by
the stapler manufacturer 1–2 (2.5–5 cm) from the ends spaced at 3–4
(8–10 cm) intervals. Continue to Step 5.
Set compressor at 70 PSI. If tongue damage occurs, lower air pressure (Figure 8).
Fasten several sacrificial boards to the floor. At least two boards, stapled side by
side, must be used to indicate proper machine adjustments.
Check for surface damage, air pressure setting, tongue damage, edge blistering,
etc., before proceeding. Make all adjustments and corrections before installation
begins. Once proper adjustments have been made, remove and destroy the boards.
Install the remainder of the floor working from several cartons.
The last 1–2 rows will need to be face-nailed when clearance does not permit blind nailing with a stapler or a brad nailer. Pre-drill
and face-nail or pneumatically nail on the tongue side, following the nailing pattern used for the first row.
General Information for Glue-Down Applications
Maximum adhesive working times: Urethane adhesive – 60 minutes; Armstrong ProConnect Professional Hardwood Flooring
Adhesive – 60 minutes. When not in use, keep the adhesive container tightly closed to prevent thickening. Thickening will cause
difficulty in spreading the adhesive.
Open times and curing times of ALL adhesives vary dependent upon subfloor porosity, air movement, humidity and room temperature.
Urethane adhesive has a shortened working time in high humidity environments, whereas the working time for ProConnect and
polymeric resin adhesives will be lengthened. In areas of low humidity, open time will be longer with urethane adhesives and shorter
with ProConnect. Adjust the amount of adhesive spread on the subfloor accordingly. The adhesive should not be applied if subfloor or
room temperature is below 60°F (16°C). WORKING TIME WILL VARY DEPENDING ON JOB SITE CONDITIONS.
Hold trowel at a minimum 45° angle (Figure 9) firmly against the subfloor to obtain a
40–60 ft.
2
(4–5.5 m
2
) per gallon spread rate. The trowel will leave ridges of adhesive and very
little adhesive between the ridges. This will allow you to still see the chalk lines between the
ridges and provide the recommended spread rate.
For additional application instructions, follow the recommendations on the adhesive container.
Proper ventilation within the room must be provided. An electric fan is helpful.
Rolling is not required, but if desired, do not do so until the adhesive has cured for two hours.
NOTE: DO NOT INSTALL FLOORING USING RUBBER MALLETS. STRIKING THE SURFACE
WITH A RUBBER MALLET MAY “BURN” THE FINISH CAUSING IRREPARABLE DAMAGE.
STEP 3: Spread the Adhesive (
Glue-Down Installations)
Spread sufficient amounts of the recommended adhesive with the recommended trowel
(
Figure 2) in an area that can be covered in 60 minutes (see adhesive information).
If necessary, nail a sacrificial row with 1(2.5 cm) nails on the dry side of your chalk line to help
hold the first row in place.
N
OTE: Avoid installing on the surface of the flooring. If necessary, distribute weight using a
kneeler board.
STEP 4: Installing the Floor (
Glue-Down Installations)
(Figures 10a–10d)
Use the longest, straightest boards available for the first two rows. For random and alternate
width products, use the widest plank for the first row. The first row of planks should be installed
with the edge of the groove lined up on the chalk line. The tongue should be facing the starting
w
all. The first row must be aligned and seated in the adhesive, as all additional rows will be
pushed back to this original row. Remove tongue to allow for expansion space, if necessary,
on the row adjoining the wall. Continue to Step 5.
When installing products wider than 3-1/4(8 cm), apply a bead of recommended wood glue
t
o all of the end grooves prior to installing into the adhesive.
When installing pieces, engage the end-joint first, as close to the side (long) tongue and
groove as possible, then slide together tightly to engage the side (long) joint tongue and
g
roove. To avoid adhesive bleed-through and memory pull-back, avoid sliding pieces through
the adhesive as much as possible when placing them in position.
During the installation occasionally remove a piece of flooring from the subfloor and inspect
t
he back for proper adhesive transfer. Adequate adhesive transfer is necessary to ensure
sufficient holding strength.
If the adhesive skins over and fails to transfer, remove and spread new adhesive to achieve
p
roper bonding.
NOTE: Clean adhesive from the surface of the floor frequently, using the recommended adhesive
cleaner. Urethane adhesives become extremely difficult to remove when cured. Do not use 3M
S
cotch-Blue™ 2080 Tape before adhesive is removed from the surface. Use clean towels,
changed frequently, to prevent haze and adhesive residue.
Check for a tight fit between all edges and ends of each plank. End-joints of adjacent rows
should be staggered 4–6(10–15 cm), when possible, to ensure a more favorable overall
appearance (Figure 4).
It may be necessary to align the product with a cut-off piece of scrap as shown
(Figure 11 – keep scrap angle low to avoid edge damage).
To eliminate minor shifting or gapping of product during installation, use 3M Scotch-Blue
2080 Tape to hold the planks together. After installation is complete, remove all of the 3M
Scotch-Blue 2080 Tape from the surface of the newly installed flooring. Do not let the tape
r
emain on the flooring longer than 24 hours. Avoid the use of masking or duct tape, which
leaves an adhesive residue and may damage the finish.
If necessary, use weights to flatten boards with bows until adhesive cures, in order to
p
revent hollow spots. Boards that cannot be flattened should be cut in length to reduce the
bow, or not used.
Be sure not to spread adhesive too far ahead of your work area (Figure 10d).
Complete the installation using this same technique for the remainder of the floor.
Avoid heavy foot traffic on the floor for at least 24 hours. Lift the furniture or fixtures back into place after 24 hours.
General Information for Floating Floors
F
loating floors can be installed over any structurally sound surface that meets or exceeds local building codes. Any width of flooring
can be installed in this manner but wider widths are preferred.
Plan the floor layout (in width) to avoid having to rip the last row narrower than 1
(2.5 cm). This may require ripping the first row to assure the last row is at least the
minimum width.
Allow 1/2(13 mm) expansion around all vertical obstructions.
STEP 3: Installing the Underlayment
(Floating Installations Only)
Install the underlayment in the same direction the hardwoodooring is to be installed.
Extend the underlayment a few inches up the wall.
Trim excess prior to installing trim or moldings.
The floating floor underlayment already has double-sided tape for ease of taping
the precut overlapping seams (Figure 12). If a non-adhesive underlayment is used,
tape all seams with the included tape.
STEP 4: Installing the Floor
(Floating Installations Only)
The first row can be installed using one of two methods after the layout has been
completed (Step 2). Allow 1/2(13 mm) expansion.
Sacrificial board: If the wall is not straight, scribe the first board (Figure 13) as
necessary to maintain alignment with the chalk line. Install a sacrificial board (with
a straight edge) using the appropriate fasteners for the subfloor. If a board is used
for the starter row make certain the groove faces the wall.
Wedges: Align the first row with the wall using wedges to maintain a 1/2(13 mm) expansion in place and to stabilize the product.
If the wall is not straight, scribe the first board (Figure 13) as necessary to maintain alignment with the chalk line.
Select the first board. All
installations should begin with the
groove side against the wall using
the longest boards available.
Apply a continuous 1/8(3 mm)
glue bead to the inside bottom of
the groove on the end of the
board. Do not apply glue to the
groove side at this time (Item C,
Figure 14). Products with the end
tongue on the left should be
installed right to left, opposite
tongues should be left to right
(Item D, Figure 14). If a sacrificial
board was used DO NOT glue
the first row to it.
Complete the first row. Cut the last board allowing for 1/2(13 mm) clearance between the wall
and the floor. (Use the remaining end of the cut board as a starter board for any row following row three). Install a wedge on the
end of the board between the hardwood flooring and the wall, allowing 1/2(13 mm) expansion space. Avoid installation of any
boards shorter than 16(40.6 cm) in the first four rows (Item F, Figure 14).
Use a pull bar to pull the last board into place from the opposite end. Install wedges into the gap and tighten (Item B, Figure 14).
If any glue gets on the surface of the flooring, wipe off immediately with a clean damp cloth.
Figure 11
16
(40.6 cm)
C
Starter Strip
Wooden Wedges
Underlayment
A
D
F
B
G
E
Always work directly in front of the plank
you are installing. Never stand or sit on any
of the planks you have already installed.
Apply a
1/8 (3 mm)
bead along
the inside
bottom of
the end
and side
groove.
“Work Zone”
Figure 14
Underlayment will install
parallel to longest wall
Pre-measured overlap
Underlayment
Les panneaux di renforcement
doivent être installés parallèlement
au mur le plus long.
Zone de recouvrement de panneaux
de renforcement pré-mesurée.
Panneaux de renforcement
El recubrimiento inferior se
instala en sentido paralelo
a la pared más larga
Superposición incluida
Recubrimiento inferior
Figure 12
chalk line
work area - adhesive
Figure 10a
chalk line
w
ork area - adhesive
groove side
231
Figure 10b
F
igure 10c
12 3
10 11 12
13
456
78 9
Figure 10d
45
˚
-90
˚
Figure 9
Figure 13
4
-
6
(10-15 cm)
F
igure 5
Figure 6
S
TARTING WALL
Multiple of width of
product + 1/4
(6 mm)
[1/2
(13 mm) for
floating floors] expansion
C
halk line
Figure 4
P
referred Alignment
face nail every
6 (15 cm)
1st row 1st row
2nd row
blind nail into
t
ongue every
3
–4(8-10 cm)
tongue
chalk line
Figure 7
Wood Plank
Figure 8
Too Low
Correct
Too High
3
Page view 2
1 2 3 4 5 6 7 8 9 10

Comments to this Manuals

No comments